2024 GPPM Result Report (1p): Annual Performance Summary of the Public Procurement Hub

Overview of the 2024 GPPM Result Report

The 2024 GPPM (Global Public Procurement Market) result report provides a one-page summary of the annual performance of the KOTRA Dhaka Trade Center's public procurement hub in 2024. The public procurement hub is a dedicated platform that supports Korean companies in winning projects in Bangladesh's government procurement market through tender intelligence, buyer matching, technical specification reviews, and local network development.

In 2024, Bangladesh's public procurement market temporarily slowed in the second half of the year due to political changes, including the August change in government. However, large-scale power and transport infrastructure projects backed by ADB and the World Bank continued to move forward, allowing Korean companies to maintain order performance broadly in line with the previous year. Against an annual support target of $200M, the hub delivered $185M, reaching 92.5% of target.

$185M
Order Support
92.5% of target
342
Tender Leads
collected and shared
67
Buyer Matching
Korean firms to procurers
12
Confirmed Awards
contracts signed
$450M
Pipeline
carried into 2025
156
Local Meetings
agencies and buyers
24
Market Reports
two per month
August
Government Change
second-half slowdown

Quarterly Performance Breakdown

Performance in 2024 varied clearly by quarter. The first quarter recorded the strongest order results thanks to contract conversions from the prior year's pipeline. In the second quarter, tender intelligence collection remained active despite procurement deceleration during Ramadan. The third quarter saw a sharp drop in new tenders following the August political transition, but the fourth quarter showed recovery as procurement activity resumed under the interim administration.

2024 GPPM Quarterly Performance
ItemQ1Q2Q3Q4Annual Total
Order Support ($M)65482844185
Tender Leads95886297342
Buyer Matching2218101767
Confirmed Awards531312
Local Meetings48422541156
Market Reports666624

Major Contracting Outcomes

Power and Energy (7 cases, $128M)
BPDB Gas Turbine$45M - Korean Company A
PGCB Transformers$32M - Korean Company B
BAPEX Drilling Parts$8M - Korean Company C
Solar Modules$43M - Korean Company D and others
Transport and Construction (5 cases, $57M)
RHD Bridge Bearings$12M - Korean Company E
LGED Equipment$8M - Korean Company F
BRTC Bus Parts$15M - Korean Company G
Rail Signaling$22M - Korean Company H

Of the 12 confirmed awards in 2024, the power and energy segment accounted for seven contracts worth $128M, representing 69% of the total. The largest awards were the BPDB gas turbine package at $45M and the PGCB transformer package at $32M, while solar module exports worth $43M emerged as a new growth area. Transport and construction generated five contracts worth $57M, led by bridge bearings for RHD and railway signaling systems. Although only one award was confirmed in the third quarter due to the political transition, the fourth-quarter recovery allowed the hub to finish the year at 92.5% of target.

2025 Outlook and Action Plan

01
$450M Pipeline Carry-Over
As of year-end 2024, a $450M pipeline is rolling into 2025. Key items include the BPDB 600MW CCPP project ($200M), the PGCB 400kV transmission line ($120M), the ADB rural transport program ($80M), and Bangladesh Railway modernization ($50M). The target conversion rate for the carry-over pipeline is 40%, equivalent to about $180M.
02
Expansion into Digital and Green Segments
In 2025, procurement monitoring will be expanded in digital infrastructure areas such as 5G and data centers, as well as green energy fields including solar and wind. ICT infrastructure investment under the Smart Bangladesh 2041 vision and power plant development tied to renewable energy targets are expected to create new opportunities.
03
Deeper Local Networks
The hub plans to build early relationships with key policymakers in the next administration following the interim government period. Meetings with new decision-makers at BPDB, PGCB, LGED, and RHD are to be completed within the first quarter, while seminars introducing Korean products and technologies will be held once each quarter.
04
Order Target of $220M (+19%)
The 2025 order-support target is set at $220M, up 19% from $185M in 2024. Segment targets are $150M for power, $40M for transport and construction, and $30M for digital and green sectors, with quarterly tracking in place. To support this goal, tender intelligence collection will be expanded to more than 400 cases.
2024 GPPM to 2025 Planning Flow
2024 Results
$185M in awards (92.5%)
Pipeline
$450M carried over
New Segments
digital and green added
Network
build ties with new government
2025 Target
$220M (+19%)
2024 Public Procurement Hub Q1 ReportReview the detailed first-quarter performance and tender pipeline for 2024
PMS Overview: Agency Analysis for BPDB, LGED, BAPEX, and PGCBSee procurement patterns and market-entry strategies across four key agencies

The 2024 GPPM result report offers a consolidated assessment of support activities for Korean companies pursuing public procurement opportunities in Bangladesh. Despite the external shock of the political transition, the hub still achieved 92.5% of its target thanks to a stable pipeline in power and energy and the continued execution of projects financed by ADB and the World Bank. In 2025, the program plans to add digital and green energy segments and expand its order target to $220M, further strengthening Korean companies' access to Bangladesh's public procurement market.

GPPMpublic procurementresult report2024performance
2024 GPPM Result Report (1p): Annual Performance Summary of the Public Procurement Hub | Dhaka Trade Portal