DX Innovation

2025–2028 EIPP Pre-Inspection Mission Plan: Field Verification and Feasibility Review

Pre-Inspection Mission Overview

The 2025–2028 EIPP (Economic Industrial Park Program) pre-inspection mission is an essential procedure to conduct on-site surveys and verify the feasibility of five priority economic zones and three key infrastructure project sites before full-scale implementation begins. Led by KDI, 12 Korean experts (spanning economics, civil engineering, energy, ICT, environment, and social sectors) and 8 Bangladeshi counterparts from BEZA and ERD will carry out 14 days of field inspections.

The mission has three core objectives. First, to identify gaps between the $500M investment targets set in the 2025–2027 mid-term roadmap and on-the-ground feasibility. Second, to quantitatively evaluate actual infrastructure readiness (power, roads, water, telecommunications) against a 120-item checklist. Third, to identify on-site risks not visible in official documents — land disputes, community grievances, labor supply constraints — through stakeholder interviews, and incorporate findings into risk mitigation plans.

14 Days
Mission Duration
5 zones + 3 infrastructure sites
12 Specialists
Korean Experts
Across 6 fields
8 Officials
Bangladeshi Counterparts
BEZA, ERD, CPTU
8 Sites
Sites to Inspect
5 zones + 3 infrastructure sites
120 Items
Checklist
Technical, economic, environmental, social
25 Sessions
Stakeholder Interviews
Institutions, companies, residents
48 Files
Pre-Inspection Documents
BEZA, ADB, World Bank materials
Mar 2025
Final Report Submission
Government deliberation schedule

Inspection Schedule and Detailed Activities

The 14-day schedule is structured as follows: Dhaka briefing (2 days) → Chittagong and Mirsarai (3 days) → Mongla (2 days) → Rajshahi (2 days) → Araihazar (2 days) → Dhaka comprehensive workshop (3 days). At each site, four key tasks run in parallel: infrastructure status survey, land condition verification, environmental baseline survey, and stakeholder interviews. The comprehensive workshop integrates on-site findings and finalizes supplementation measures and project adjustments.

Pre-Inspection Mission Schedule and Key Deliverables
DayLocationKey ActivitiesResponsible TeamDeliverableKey Verification Points
Days 1–2DhakaERD and BEZA policy briefings, incentive status verificationKDI OverallStatus reportBEZA Act amendment status, one-stop service operational reality
Days 3–5Chittagong / MirsaraiPort accessibility, power grid, zone Phase 1 siteCivil / EnergyField assessmentPower reserve margin, port-to-zone travel time, land acquisition progress rate
Days 6–7MonglaLNG terminal, energy and chemical zone, portEnergy / EnvironmentFeasibility memoLNG supply schedule, wastewater treatment plan, environmental impact survey
Days 8–9RajshahiAgri-food zone, water resources, cold storage infrastructureEnvironment / AgricultureEnvironmental baseline reportGroundwater quality, cold-chain logistics access, agricultural land status
Days 10–11AraihazarICT zone, fiber optic infrastructure, data center siteICTTechnical assessmentFiber optic coverage, 5G infrastructure, power stability
Days 12–14DhakaComprehensive workshop, Gap Analysis, draft final reportAll teamsFinal report (draft)120-item aggregate rating, risk classification, supplementation measures finalized

Feasibility Verification Checklist Framework

The 120-item checklist is organized across four domains: technical (40 items), economic (30 items), environmental (25 items), and social (25 items). Each item is rated on a three-tier scale: "Good (Green) / Caution (Yellow) / Below Standard (Red)." Red-rated items require a supplementation plan as a precondition for project approval. Yellow-rated items allow the project to proceed with an attached mitigation plan.

Key Evaluation Items by Checklist Domain
DomainItemsCore IndicatorsBenchmarkRed Rating Criteria
Technical40 itemsPower stability, road access, water supplyPower reserve 15%+, port within 4 hoursPower reserve below 5%, no arterial road connection
Economic30 itemsEIRR, NPV, payback period, employment multiplierEIRR 12%+, payback within 15 yearsEIRR below 8%, no market viability
Environmental25 itemsWater and soil contamination, wastewater treatment, climate vulnerabilityWithin WHO standards, ZLD feasibleHeavy metal contamination confirmed, treatment infeasible
Social25 itemsDisplaced population scale, compensation plan, employment absorptionFewer than 500 displaced, compensation completeUnresolved compensation disputes, large-scale forced displacement

Key Verification Points by Zone

Mirsarai (Light Manufacturing)
PowerCompletion status of dedicated 345kV substation for the 30,000-acre zone
PortOpening date of direct road link to Chittagong New Port (4km)
Smart Park SiteLand ownership confirmation for the 500-acre parcel
EnvironmentCoastal lowland flooding risk (flood history on record)
Araihazar (ICT and Electronics)
Fiber OpticsPGCB and BTCL 100Gbps dark fiber availability
PowerFeasibility of data center-grade redundant power supply
TransportHighway accessibility to Dhaka city center (30km)
WorkforceBUET and IUB graduate supply pipeline

Stakeholder Interview Plan

A total of 25 stakeholder interviews are scheduled over the 14 days. The purpose is to identify on-site risks and opportunity factors that are difficult to assess from official documents alone. In particular, the actual operational experience of existing tenant companies provides the most practically useful reference information for Korean companies.

01
BEZA Local Offices (5 sessions)
Understand zone-by-zone operational status, complaint patterns from existing tenants, infrastructure improvement needs, and actual perception of incentives. Verify actual one-stop service processing time (target: 7 business days) versus current reality.
02
Existing Tenant Companies (8 sessions)
Assess whether promised incentives have been delivered, actual operating costs, experienced reliability of power and water supply, labor procurement status, and key difficulties. Compare experiences across nationalities including Chinese, Japanese, and Indian companies.
03
Local Community Representatives (5 sessions)
Understand land compensation issues (whether unresolved disputes exist), actual local employment rates, environmental concerns (noise, water quality, dust), and community attitudes toward future zone expansion.
04
Infrastructure Operators (4 sessions)
BPDB (power), DPHE (water), BTCL (telecommunications), Chittagong Port Authority (logistics). Current supply capacity, timeline for meeting zone demand, expansion investment plans, and financing status.
05
ADB and World Bank Local Offices (3 sessions)
Review status of ongoing loans related to Bangladesh economic zones, environmental and social safeguard issues, possibilities for joint projects with Korea, and 2025–28 financing consultation channels.

Expert Team Composition and Roles

Korean Expert Team Composition (12 Members)
FieldCountInstitutionKey RoleField Deployment
Economics and Industrial Policy2KDIOverall coordination, EIRR analysisFull schedule
Civil Engineering and Infrastructure2KDI, KICTRoad, port, and land site assessmentMirsarai, Chittagong
Energy2KETEP, KOICAPower, LNG, and renewable energy feasibilityMongla, Mirsarai
ICT2NIA, IITPTelecom infrastructure and smart city assessmentAraihazar, Dhaka
Environment2KEIEnvironmental baseline survey, ZLD feasibilityAll zones
Social and Labor2KLIStakeholder interviews, social impact assessmentFull schedule

Inspection Deliverables and Utilization

Immediate On-Site Deliverables
Checklist Assessment Sheet120-item Green / Yellow / Red ratings
Photos and VideoInfrastructure status documentation for each zone
Interview TranscriptsFull records of all 25 stakeholder interviews
Baseline Data CollectionPower, water, and telecommunications measurements
Post-Report Utilization
Gap AnalysisPlan-to-reality gaps quantified by item
Risk RegisterMitigation plans for the top 10 high-risk items
Investment Interest PackageInformation for 10 interested Korean firms
Next Step ScheduleGroundbreaking, MOU, and investment roadshow dates confirmed

Post-Inspection Procedures and Project Finalization Roadmap

EIPP Project Finalization Procedure After Pre-Inspection Mission
On-Site Inspection (14 days)
5 zones + 3 sites, 120-item checklist, 25 stakeholder interviews
Report Writing (30 days)
Gap Analysis, risk classification, supplementation measures drafted
Government Deliberation (60 days)
KDI → MoF → BEZA joint deliberation, Red item supplementation verified
Project Adjustments Finalized
Timeline, budget, and priority zone sequence finalized; groundbreaking permit issued
Launch (2025 Q2)
Smart park groundbreaking ceremony, 1st investment roadshow, first MOU signed
Quarterly Monitoring
KDI–BEZA joint review, semi-annual reports, ongoing project adjustments
2025–2027 EIPP Mid-Term Roadmap3-year investment targets, smart industrial park, and annual milestones
Chittagong and Mirsarai EIPPInvestment analysis of eastern Bangladesh's largest economic zone and Korean firm entry opportunities
EIPPPre-InspectionMission PlanField VerificationFeasibility Review
2025–2028 EIPP Pre-Inspection Mission Plan: Field Verification and Feasibility Review | Dhaka Trade Portal